|
|
|
SOUTHERN PACIFIC REPORTS INCREASED HEAVY OIL RESERVES AT
SENLAC CALGARY, Alberta – April 26, 2010 Southern
Pacific Resource Corp. (“Southern Pacific” or the “Company”)
(TSX-V:STP) is pleased to announce that the estimate of the total proved plus
probable (“2P”) recoverable heavy oil reserves within its 100%-owned
Senlac Thermal
Project in Saskatchewan has increased 14% from the previous estimate to 10.4
million barrels (MMbbl). This equates to a net present value before tax of
$193.9 million (discounted at 10% based on April 1, 2010 forecast pricing).
Additionally, 20.8 MMbbl of recoverable oil at Senlac has been assigned to the
total proved plus probable plus possible (“3P”) reserves category, an
increase of 33%. The 3P reserves have a corresponding net present value before
tax of $334.2 million (discounted at 10% based on April 1, 2010 forecast
pricing). The
updated reserves report for Senlac was completed by GLJ Petroleum Consultants
of Calgary (“GLJ”) effective April 1, 2010. This is the first independent reserves
evaluator’s report completed on Senlac since Southern Pacific acquired
the property on November 3, 2009 for a purchase price of $89.3 million after
adjustments. A summary of the previous reserves evaluation effective December
31, 2008 is included in a material change report filed by Southern
Pacific on SEDAR on October 9, 2009. Senlac
has produced a total of approximately 2.1 MMbbl of heavy oil between the
effective dates of the two reserves
reports. Southern Pacific attributes the increase in reserves to better
performance from existing wells and the
wells drilled subsequent to the December 2008 report. The following table summarizes GLJ’s estimate of the
reserves at the Senlac Thermal Project:
(1)
The
before tax present values are based on GLJ’s April 1, 2010 forecast pricing. (2)
Estimates
of values disclosed do not represent fair market value. Senlac Operational Update The
Senlac Thermal Project has delivered significant cash flow since Southern
Pacific acquired the property in November 2009. Between the acquisition date and the
end of March 2010, cash flow after operating costs, capital and
royalties is estimated to have been $26.9 million, an average of $5.4 million
per month. Production averaged 4,430 bbl/d over the same period, which exceeds
expectations despite lost days of production due to some unusual mechanical
and power issues that have since been resolved. The project has averaged 4,600
bbl/d in April. Since
acquiring the Senlac Thermal Project, Southern Pacific has reprocessed and
interpreted the 3D seismic data that was included with the
acquisition, developed a geologic and reservoir model of the project, and
completed a full field development plan. The next phase of development
involves the drilling of two horizontal wedge wells in the Phase G pad. These
wells have been licensed, the drilling rig has been contracted and they are
expected to spud in early May. Two Steam- Assisted Gravity Drainage (SAGD) well
pairs in Phase H are expected to be drilled in the fall of 2010 to complete
this year’s development activities. The wedge wells and the Phase H SAGD
well pairs are the initial phases of Southern Pacific’s development plan,
which targets to keep the facilities processing between 4,000 and 5,000 bbl/d of
heavy oil on an ongoing basis. Key
components of Southern Pacific’s success to date are the 19 field staff
members at Senlac who joined the Company with the acquisition. They have gone to
great lengths to ensure a smooth transition of operations and have embraced
and enhanced the Company’s corporate culture and knowledge base. Company Reserves and Contingent
Resources In
addition to the Senlac heavy oil project, Southern Pacific has an average 81%
working interest in 301 sections of Alberta’s oil sands. This total includes a
previously announced agreement to purchase the remaining 20% interest in the
Company’s McKay leases, which is expected to close on June 1, 2010 (see
press release dated March 19, 2010). On
March 25, 2010, Southern Pacific announced a significant increase in the value
of its oil sands lands in McKay. In a reserves report effective March 15, 2010, GLJ
estimated the 2P reserves at McKay to be 168.1 MMbbls, equivalent
to a net present value before tax of $368 million (discounted at 10%). This is
based on a 100% working interest at McKay. When the value of the reserves at
Senlac are combined with the value of the reserves at McKay, the
total net present value before tax of Southern Pacific’s 2P reserves is
estimated to be $562 million (discounted at 10%). The
Senlac and McKay reserves make up approximately 99% of the Company’s total
2P reserves and value. The remaining 1% of Southern Pacific’s reserves
consists of conventional oil and gas assets. These reserves will not be updated
until the fiscal year end (June 30, 2010). In
addition to 2P heavy oil and bitumen reserves, Southern Pacific has 116.7
MMbbl of best estimate (P50) contingent
bitumen resources identified in the McKay area (see press release dated March
25, 2010). GLJ is now focused on completing an assessment of the prospective
and contingent bitumen resources over the Company’s remaining lands in the
Athabasca oil sands, which will complete the reserves and resource evaluation
work required for a comprehensive fiscal year-end report. For further information, please
contact: Byron Lutes, President & CEO 403-269-1529 Jeff Barefoot, Vice President, Resource Development 403-269-1528 Or visit our website at:
www.shpacific.com. Neither the TSX Venture Exchange nor its Regulation Services Provider (as
that term is defined in the policies of Readers’ Advisory Barrel of Oil Equivalent: Where amounts are expressed on a barrel of oil
equivalent (“boe ”) basis, natural gas volumes have been converted to boe at a ratio of 6,000 cubic feet of natural gas to one barrel of oil
equivalent. This conversion ratio is based upon an energy equivalent conversion
method primarily applicable at the burner tip and does not represent value
equivalence at the wellhead. Boe figures may be misleading,
particularly if used in isolation. Definitions “Best
estimate (P50)” means the best estimate of the quantity of petroleum that
will actually be recovered. It is equally likely that the actual remaining
quantities recovered will be greater or less than the best estimate. If
probabilistic methods are used, there should be at least a 50 percent
probability (P50) that the quantities actually recovered will equal or exceed
the best estimate. “Contingent resources” means those quantities of petroleum
estimated, as of a given date, to be potentially recoverable from known accumulations using established technology or technology under
development, but which are not currently considered to be commercially recoverable due to one or more contingencies. Contingencies may include
factors such as economic, legal, environmental, political, and regulatory matters or a lack of markets. It is also appropriate to
classify as contingent resources the estimated discovered recoverable quantities
associated with a project in the early evaluation stage. “Prospective resources” means those
quantities of oil and gas estimated on a given date to be potentially
recoverable from undiscovered accumulations. They are
technically viable and economic to recover. “Probable reserves” means those additional reserves that are
less certain to be recovered than proved reserves. It is equally likely that the
actual remaining quantities recovered will be greater or less than
the sum of the estimated proved plus probable reserves. “Possible reserves” means those additional reserves that are
less certain to be recovered than probable reserves. There is a 10% probability
that the quantities recovered will equal or exceed the sum of
the estimated proved plus probable plus possible reserves. “Proved reserves” means those reserves that can be estimated
with a high degree of certainty to be recoverable. It is likely that the actual remaining quantities recovered will exceed the estimated proved reserves. The estimates of reserves and future net revenue for additional properties
may not reflect the same confidence level as estimates of reserves and future net revenue for all properties, due to the effects
of aggregation. Safe Harbour This news release contains certain “forward-looking information”
within the meaning of such statements under applicable securities law including
estimates as to: future production, operations, operating costs, commodity
prices, administrative costs, commodity price risk management activity, acquisitions and dispositions, capital spending,
access to credit facilities, income and oil taxes, regulatory changes, and other
components of cash flow and earnings anticipated discovery of commercial volumes
of bitumen, the timeline for the achievement of anticipated
exploration, anticipated results from the current drilling program and, subject
to regulatory approval and commercial factors, the commencement
or approval of any SAGD project. Forward-looking information is frequently characterized by words such as
“plan”, “expect”, “project”, “intend”, “believe”,
“anticipate”, “estimate”, “may”, “will”, “potential”,
“proposed” and other similar words, or statements that certain events or
conditions “may” or “will” occur. These statements are only predictions. Forward-looking information
is based on the opinions and estimates of management at the date the statements are made and are subject to a variety of risks and
uncertainties and other factors that could cause actual events or results to
differ materially from those projected in the
forward-looking statements. These factors include, but are not limited to,
variation between estimates of reserves data and actual results, the inherent
risks involved in the exploration and development of conventional oil and gas
properties and of oil sands properties, difficulties or
delays in start-up operations, the uncertainties involved in interpreting
drilling results and other geological data, fluctuating oil prices, the possibility of unanticipated costs and
expenses, uncertainties relating to the availability and costs of financing
needed in the future and other factors including unforeseen delays. As an oil
sands enterprise in the development stage, with some heavy oil and conventional production, Southern Pacific faces risks including those
associated with exploration, development, start-up, approvals and the continuing ability to access sufficient capital from external sources if
required. Actual timelines associated may vary from those anticipated in this
news release and such variations may be material. Industry related risks could
include, but are not limited to, operational risks in exploration,
development and production, delays or changes in plans, risks associated to the
uncertainty of reserve estimates, health and safety risks
and the uncertainty of estimates and projections of production, costs and
expenses. For a description of the risks and uncertainties facing Southern
Pacific and its business and affairs, readers should refer to Southern
Pacific’s most recent Annual Information Form. Southern Pacific undertakes
no obligation to update forward-looking statements if circumstances or
management’s estimates or opinions should change, unless required
by law. The reader is cautioned not to place undue reliance on this forward-looking information. | ||||||||||||||||||||||||||||